- Start with one business use case and its acceptance criteria.
- Estimate against explicit assumptions and cost drivers.
- Plan migration, testing and support ownership before launch.
1. Define the first business use case
Start with a specific workflow and the people who depend on it. That could mean engineering document control, policy approvals or business-record processing. Identify where the current process causes delays, duplicated effort or weak visibility.
OpenText describes Documentum as a platform for managing enterprise content and connected processes. Implementation turns those platform capabilities into an operating model for your organization.
- Documents, records and business processes in scope.
- Creators, reviewers, approvers and external participants.
- Required metadata, search behavior and document relationships.
- Access restrictions, retention, disposal and evidence requirements.
- Expected volumes, transaction patterns and service hours.
Agree what the first release must achieve. An unrestricted request to manage every enterprise document is difficult to price, test or accept.
2. Understand what drives implementation cost
There is no dependable implementation price without an agreed scope and assumptions. Ask for an estimate that makes the drivers visible, identifies client responsibilities and distinguishes launch requirements from later improvements.
| Cost driver | What changes the effort | What to establish during discovery |
|---|---|---|
| Process complexity | Approval paths, exceptions, escalations and business rules | Priority workflows, owners and acceptance scenarios |
| Content migration | Source quality, volume, versions, renditions and relationships | Inventory, sample content, mapping and reconciliation scope |
| Integration | Connected systems, interface quality and error handling | System owners, contracts, dependencies and failure scenarios |
| Customization | Requirements that need extensions beyond configuration | Supported options, maintainability and upgrade implications |
| Governance | Permissions, retention, audit evidence and business controls | Approved access model and information-governance requirements |
| Testing and recovery | Performance, security, restoration and industry-specific acceptance | Test data, environments, evidence and approval owners |
| Adoption | Training, communications and changed working practices | User groups, training needs and support model |
Separate software licensing and infrastructure from implementation services. Include operating support, maintenance and future change in the overall budget. A low initial build estimate can miss substantial migration or support responsibilities.
3. Agree the content model and architecture
Define document types, metadata, classification, folder or relationship rules, access controls and lifecycle behavior. Review design decisions with business, security and operations owners before configuration work becomes expensive to change.
Decide which requirements can use supported configuration and which need development. Record the reason for each extension, how it will be tested and who will maintain it. Include identity, search, capture, viewing and enterprise integration dependencies in the architecture.
4. Deliver in phases with clear outputs
| Phase | Expected outputs | Decision before proceeding |
|---|---|---|
| Discovery and assessment | Prioritized requirements, content inventory, dependencies and assumptions | Business scope and acceptance criteria agreed |
| Architecture and design | Content model, access rules, workflow and integration designs | Business, security and support owners approve the design |
| Configuration and development | Configured processes, approved extensions and demonstrations | Priority user scenarios work and gaps have owners |
| Migration and testing | Migration rehearsals, reconciliation and end-to-end test evidence | Critical acceptance criteria met or exceptions approved |
| Launch and handover | Production transition, training, runbooks and support ownership | Operations accepts the service and outstanding work is controlled |
Demonstrate working business scenarios throughout delivery. Regular feedback is more useful than waiting for users to see the full solution during final acceptance.
5. Keep changes to scope visible
New requirements often emerge when users see the system. Use a decision log to record each proposal, its business value and its effect on effort, schedule, risk and support.
Separate launch-critical requirements from improvements that can follow. The sponsor should be able to see the trade-off and approve the change; a revised requirement should not silently become an unplanned delivery commitment.
6. Plan migration and acceptance before launch
Define what must move from existing repositories, how it maps into Documentum and how results will be reconciled. Test representative files, versions, metadata, permissions and linked processes. Agree which exceptions need resolution and who may approve an alternative treatment.
Use end-to-end acceptance scenarios that reflect real work: create or import a document, classify it, route it for review, find it and retrieve the right version with the intended access. Include integration failures, performance and recovery. The Documentum migration validation guide provides a more detailed evidence model.
7. Prepare for operation before go-live
Assign ownership for monitoring, incidents, access requests, scheduled jobs and software maintenance. Support teams need configuration records, recovery procedures, known limitations and integration contacts. Business teams need ownership rules for documents, metadata quality and approvals.
Agree the initial support period, service hours, escalation route and transition to ongoing support. Training and operational readiness are part of delivery, not tasks to leave until after the launch date.
Questions to ask an implementation partner
- What assumptions and client dependencies does the estimate rely on?
- Which deliverables, exclusions and acceptance criteria are included?
- Who owns migration mapping, reconciliation and exception decisions?
- How will integrations, permissions and recovery be tested?
- What documentation and knowledge transfer will support teams receive?
- What happens when the initial support period ends?
If you are modernizing an existing installation rather than starting a new implementation, the Documentum upgrade checklist helps separate upgrade dependencies from new business requirements.
Working checklist
Use this checklist to record your review. Selections stay in this browser view and are not submitted.
0 of 6 checked
Frequently asked questions
How much does an OpenText Documentum implementation cost?
The cost depends on scope, process complexity, content migration, integrations, customization, governance, testing and adoption. Establish requirements and assumptions before estimating. Keep licensing, infrastructure and ongoing operation visible as separate budget items.
How long does a Documentum implementation take?
Timing depends on the release scope, dependencies, design decisions, migration workload, environment availability and acceptance requirements. A phased estimate should follow discovery rather than rely on a generic fixed duration.
Can Documentum be configured without custom development?
Some requirements can be met with supported configuration; others may need extensions or integrations. Assess the installed product options and requirements before committing, and consider future maintenance and upgrade effects.
Should migration be included in the implementation scope?
Yes, when existing content is needed for the business use case. State the source inventory, mappings, versions, permissions, evidence and exceptions explicitly. Migration should not be assumed to mean copying only current files.
What should be handed over at go-live?
Provide architecture and configuration records, operating and recovery procedures, monitoring responsibilities, integration contacts, known issues, training material and a defined support/escalation model.